Electricity Regulation Act 1999
Number 23 of 1999
ELECTRICITY REGULATION ACT 1999
REVISED
Updated to 25 July 2024
This Revised Act is an administrative consolidation of the Electricity Regulation Act 1999. It is prepared by the Law Reform Commission in accordance with its function under the Law Reform Commission Act 1975 (3/1975) to keep the law under review and to undertake revision and consolidation of statute law.
All Acts up to and including the Courts, Civil Law, Criminal Law and Superannuation (Miscellaneous Provisions) Act 2024 (30/2024), enacted 23 July 2024, and all statutory instruments up to and including the Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) (No. 1) Order 2024 (S.I. No. 377 of 2024), made 25 July 2024, were considered in the preparation of this Revised Act.
Disclaimer: While every care has been taken in the preparation of this Revised Act, the Law Reform Commission can assume no responsibility for and give no guarantees, undertakings or warranties concerning the accuracy, completeness or up to date nature of the information provided and does not accept any liability whatsoever arising from any errors or omissions. Please notify any errors, omissions and comments by email to
revisedacts@lawreform.ie.
Number 23 of 1999
ELECTRICITY REGULATION ACT 1999
REVISED
Updated to 25 July 2024
ARRANGEMENT OF SECTIONS
Preliminary and General
Section |
|
1. |
|
2. |
|
2A. |
Position of interconnectors as respects transmission system. |
3. |
|
4. |
|
5. |
|
6. |
|
7. |
Establishment of Commission for Electricity Regulation
8. |
|
8A. |
|
8B. |
Commission and working arrangements as respects Single Electricity Market. |
9. |
|
9A. |
|
9B. |
|
9BA. |
Functions of Commission relating to the Single Electricity Market. |
9BB. |
|
9BC. |
|
9BD. |
|
9C. |
|
9D. |
|
9E. |
|
9EA. |
|
9F. |
|
9G. |
|
9H. |
|
9I. |
|
9J. |
|
9JA. |
|
9JB. |
|
9JC. |
|
9JD. |
Restricting or prohibiting LPG or natural gas activities in emergencies. |
9JE. |
|
9JF. |
|
9JG. |
|
9K. |
Extension of gas safety provisions to liquefied petroleum gas. |
9L. |
|
9M. |
|
9N. |
Functions of the Commission under Part IIA relating to petroleum safety. |
9O. |
|
9P. |
Functions of Commission in relation to Electricity Costs Emergency Benefit Scheme. |
9Q. |
Functions of Commission in relation to Electricity Costs Emergency Benefit Scheme II |
9R. |
|
10. |
|
10A. |
|
11. |
|
12. |
|
13. |
Regulation of petroleum activities
13A. |
|
13B. |
|
13C. |
|
13D. |
|
13E. |
Prohibition on carrying on designated petroleum activity without safety permit. |
13F. |
|
13G. |
|
13GA. |
|
13H. |
|
13HA. |
|
13I. |
|
13J. |
|
13K. |
|
13KA. |
|
13KB. |
|
13KC. |
|
13L. |
|
13M. |
|
13MA. |
|
13N. |
|
13O. |
|
13OA. |
|
13P. |
|
13Q. |
|
13R. |
|
13S. |
|
13T. |
|
13U. |
|
13V. |
|
13W. |
|
13X. |
|
13Y. |
|
13Z. |
|
13AA. |
|
13AB. |
|
13AC. |
|
13AD. |
Licences and Authorisations
Registration of market participants that are not electricity undertakings
28A. |
|
28AB. |
|
28AC |
Registration for purpose of engaging in electricity activity. |
28AD. |
|
28AE. |
|
28AF. |
|
28AG. |
Appeal Panels
29. |
|
30. |
|
31. |
Orders for establishment of Appeal Panels and related matters. |
32. |
Access to Transmission and Distribution Systems
Public Service Obligations and Transitional Arrangements
39. |
|
40. |
Emergency measures in event of a crisis
40A. |
Carbon revenue levy
40B. |
|
40C. |
|
40D. |
|
40E. |
|
40F. |
|
40G. |
|
40H. |
|
40I. |
|
40J. |
|
40K. |
|
40L. |
|
40M. |
Consequential Repeals and Amendments
41. |
|
42. |
|
43. |
|
44. |
|
45. |
|
46. |
Miscellaneous
47. |
|
48. |
|
49. |
|
50. |
|
51. |
|
52. |
|
53. |
Amendment of section 2(2) of Electricity (Supply) (Amendment) Act, 1949. |
54. |
Repeal of section 2(3), (4) and (6) of Electricity (Supply) (Amendment) Act, 1949. |
Power To Carry out investigations and impose administrative sanction
The Commission for Electricity Regulation
Single electricity market
Categorisation of accounts
Combined heat and power
provisions applicable to oral hearings conducted pursuant to section 58 or 60
Acts Referred to |
||
Acquisition of Land (Assessment of Compensation) Act, 1919 |
1919, c. 20 |
|
Companies Acts, 1963 to 1990 |
||
Courts Act, 1981 |
||
Electricity (Supply) Act, 1927 |
||
Electricity (Supply) Acts, 1927 to 1995 |
||
Electricity (Supply) (Amendment) Act, 1949 |
||
European Parliament Elections Act, 1997 |
||
Freedom of Information Act, 1997 |
||
Petty Sessions (Ireland) Act, 1851 |
14 & 15 Vict., c. 93 |
Number 23 of 1999
ELECTRICITY REGULATION ACT 1999
REVISED
Updated to 25 July 2024
AN ACT TO ENABLE EFFECT TO BE GIVEN TO DIRECTIVE NO. 96/92/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL OF 19 DECEMBER 1996(1), TO ESTABLISH A BODY KNOWN AS AN COIMISIÚN UM RIALÁIL LEICTREACHAIS OR IN THE ENGLISH LANGUAGE THE COMMISSION FOR ELECTRICITY REGULATION, TO GIVE POWER TO THAT COMMISSION TO GRANT LICENCES TO GENERATE AND SUPPLY ELECTRICITY AND TO GRANT AUTHORISATIONS TO CONSTRUCT GENERATING STATIONS, TO PROVIDE FOR ACCESS TO THE TRANSMISSION OR DISTRIBUTION SYSTEM BY HOLDERS OF LICENCES, HOLDERS OF AUTHORISATIONS OR BY ELIGIBLE CUSTOMERS, TO AMEND AND REPEAL CERTAIN PROVISIONS OF THE ELECTRICITY (SUPPLY) ACT, 1927 AND TO PROVIDE FOR RELATED MATTERS. [11th July, 1999]
BE IT ENACTED BY THE OIREACHTAS AS FOLLOWS:
Annotations
Modifications (not altering text):
C1
Collective citation by Maritime Area Planning Act 2021, s.1(3), S.I. No. 394 of 2022.
C2
Application of collectively cited Electricity and Gas Regulation Acts 1999 to 2002 affected (21.09.2011) by European Communities (Birds and Natural Habitats) Regulations 2011 (S.I. No. 477 of 2011), regs. 42(22), 46(3), 63(2) and sch. 2, in effect as per reg. 1(3).
Screening for Appropriate Assessment and Appropriate Assessment of implications for European Sites
42. ...
(22) Notwithstanding any provision of any statute listed in the Second Schedule that provides for the consent for a plan or project to which this Regulation applies to be obtained by default on the failure of the public authority to provide a response within a specified timescale or otherwise, that provision shall not have effect in respect of any plan or project to which this Regulation applies
...
Review of existing plans
46. ...
(3) For the purposes of this Regulation, a decision, including a decision to adopt or undertake, or give approval for a plan, may include those adopted, undertaken or approved pursuant to any of the enactments set out in the Second Schedule to these Regulations.
...
General provisions regarding licences etc
63. ...
(2) A licence, consent, permission, permit, derogation or other authorisation given under these Regulations or under any of the enactments referred to in the Second Schedule may include conditions requiring compliance with any guideline or code of practice issued under Regulation 71 or such provisions thereof as may be specified in the conditions.
...
SECOND SCHEDULE
Number |
Year |
Short Title/Citation |
... |
... |
... Electricity and Gas Regulations Acts 1999 to 2002 ... |
C3
Functions transferred and “Minister for” and “Department of Public Enterprise” construed (18.06.2002) by Communications, Energy and Geological Survey of Ireland (Transfer of Departmental Administration and Ministerial Functions) Order 2002 (S.I. No. 300 of 2002), arts. 3 and 4, subject to transitional provisions in arts. 5-9.
3. (1) The administration and business in connection with the exercise, performance or execution of any functions transferred by Article 4 of this Order are transferred to the Department of the Marine and Natural Resources.
(2) References to the Department of Public Enterprise contained in any Act or instrument made thereunder and relating to any administration and business transferred by paragraph (1) of this Article shall, on and after the commencement of this Order, be construed as references to the Department of the Marine and Natural Resources.
4. (1) The functions vested in the Minister for Public Enterprise -
(a) by or under any of the enactments or the provisions of the enactments mentioned in Part 1 of the Schedule to this Order,
(b) under the Regulations mentioned in Part 2 of that Schedule, and
(c) in relation to the Geological Survey of Ireland, are transferred to the Minister for the Marine and Natural Resources.
(2) References to the Minister for Public Enterprise contained in any Act or instrument made thereunder and relating to any functions transferred by this Article shall, on and after the commencement of this Order, be construed as references to the Minister for the Marine and Natural Reso(fb)(
SCHEDULE
PART 1.
Enactments and provisions of enactments, functions under which are transferred from the Minister for Public Enterprise to the Minister for the Marine and Natural Resources.
...
Electricity and Gas Regulation Acts 1999 to 2002
...