Electricity Regulation Act 1999 (Public Service Obligations) Order 2002
F99[SCHEDULE 3
In this Schedule—
"biomass" means the biodegradable fraction of products, waste and residues from biological origin from agriculture (including vegetal and animal substances), forestry and related industries including fisheries and aquaculture, as well as the biodegradable fraction of industrial and municipal waste;
"CHP" means combined heat and power;
"hydro project" means any hydro-powered electricity generating plant with a maximum export capacity of or less than 5 MW which is connected directly to the electricity network and metered independently of any other electricity generating plant;
"LFG" means landfill gas;
"large scale wind project" means an onshore wind project with a maximum export capacity greater than 5 MW which is connected directly to the electricity network and metered independently of any other electricity generating plant;
"small scale wind project" means any wind-powered electricity generating plant with a maximum export capacity of or less than 5 MW which is connected directly to the electricity network and metered independently of any other electricity generating plant.
|
(1) Ref. No. |
(2) REFIT Power Purchase Agreement Reference |
(3) Supplier |
(4) Electricity generator |
(5) Generation plant Description |
(6) Energy source of electricity |
(7) Capacity Accepted into REFIT (MW) |
|
1 |
1/5/2 |
Energia Customer Solutions Ltd. |
Reirk Energy Ltd. |
Dromdeeveen, Ballagh, Co. Limerick |
Large Scale Wind Project |
10.500 |
|
2 |
1/5/5 |
Energia Customer Solutions Ltd. |
Bawnmore Windfarm Ltd. |
Carriganima, Macroom, Co. Cork |
Large Scale Wind Project |
14.990 |
|
3 |
1/5/26 |
Energia Customer Solutions Ltd. |
Corkermore Windfarm Ltd. |
Corkermore Windfarm, Corkermore, Killybegs, Co. Donegal |
Large Scale Wind Project |
9.990 |
|
4 |
1/5/30 |
Energia Customer Solutions Ltd. |
Knocknalour Wind Farm Ltd. |
Knocknalour, Bunclody, Enniscorthy, Co. Wexford |
Small Scale Wind Project |
4.600 |
|
5 |
1/5/38 |
Energia Customer Solutions Ltd. |
Carrigcannon Wind Farm Ltd. |
Carragraigue, Rathcoole, Mallow, Co. Cork |
Large Scale Wind Project |
20.000 |
|
6 |
1/5/54 |
SSE Airtricity Ltd. |
Limerick West Windfarm Ltd. |
Rathcahill West, Tournafulla, Co. Limerick |
Large Scale Wind Project |
12.500 |
|
7 |
1/5/69 |
Energia Customer Solutions Ltd. |
Holyford Windfarm Ltd. |
Hollyford Windfarm, Glenough Upper, Hollyford, Co. Tipperary |
Large Scale Wind Project |
9.000 |
|
8 |
1/5/70 |
SSE Airtricity Ltd. |
Redwind Energy Phase 3 Ltd. |
Meenagrauv, Ballybofey, Stranorlar, Co. Donegal |
Small Scale Wind Project |
3.600 |
|
9 |
1/5/79 |
Bord Gáis Energy Ltd. |
Templederry Windfarm Ltd. |
Templederry Windfarm Knockmeale, Boherlody & Lisgarriff, Dolla, Nenagh, Co. Tipperary |
Small Scale Wind Project |
4.600 |
|
10 |
1/5/87 |
Energia Customer Solutions Ltd. |
Glenough Windfarm Ltd. |
Glenough Windfarm, Glenough, Co. Tipperary |
Large Scale Wind Project |
33.000 |
|
11 |
1/5/93 |
Energia Customer Solutions Ltd. |
Powercon Wind Energy Ltd. |
Carrowleagh Windfarm, Carrowleagh, Bonniconlon, Co. Mayo |
Large Scale Wind Project |
34.150 |
|
12 |
1/5/94 |
Energia Customer Solutions Ltd. |
West Clare Windfarm (Services) Ltd. |
Seltannaveeny Windfarm, Seltannaveeny, Arigna, Co. Roscommon |
Small Scale Wind Project |
4.600 |
|
13 |
1/5/98 |
SWS Green Energy Ltd. |
Garracummer Windfarm Ltd. |
Garracummer, Moanvaun, Reisk, Tooreen & Falleenafinnooga Hollyford, Co. Tipperary |
Large Scale Wind Project |
36.900 |
|
14 |
1/5/99 |
SSE Airtricity Ltd. |
Western Power Ltd. |
Lenanavea, Castlebar, Co. Mayo |
Small Scale Wind Project |
4.500 |
|
15 |
1/5/100 |
SWS Green Energy Ltd. |
Ballymartin Windfarm Ltd. |
Ballymartin Windfarm, Ballymartin, Brabstown, Co. Kilkenny |
Large Scale Wind Project |
6.000 |
|
16 |
1/5/103 |
Indaver Energy Ltd. |
Indaver Ireland Ltd. |
Carranstown, Duleek Co. Meath |
Biomass |
15.180* |
|
17 |
1/5/105 |
ESB |
Hibernian Windpower Ltd. |
Grouselodge Windfarm, Ardagh, Co. Limerick |
Large Scale Wind Project |
15.000 |
|
18 |
1/5/106 |
Energia Customer Solutions Ltd. |
Caherciveen Wind Ltd. |
Caherciveen Windfarm, Knockaneden, Caherciveen, Co. Kerry |
Large Scale Wind Project |
9.000 |
|
19 |
1/5/113 |
Energia Customer Solutions Ltd. |
Bawnmore Windfarm Ltd. |
Cahernafulla, Coachford Co. Cork |
Large Scale Wind Project |
9.000 |
|
20 |
1/5/119 |
Energia Customer Solutions Ltd. |
Ballynancoran Wind Farm Ltd. |
Ballynancoran Windfarm, Ballynancoran, Donishal, Ferns, Co. Wexford |
Small Scale Wind Project |
4.000 |
|
21 |
1/5/121 |
SSE Airtricity Ltd. |
Carrons Windfarm Ltd. |
Carrons Windfarm, Dunmoylan, Shanagolden, Co. Limerick |
Small Scale Wind Project |
5.000 |
|
22 |
1/5/129 |
Bord Gáis Energy Ltd. |
Menard Ltd. |
Skrine Windfarm, Athleague, Co. Roscommon |
Small Scale Wind Project |
4.600 |
|
23 |
1/5/130 |
Bord Gáis Energy Ltd. |
Fairbourne Commercial Ltd. |
Leabeg Windfarm, Ferbane, Co. Offaly |
Small Scale Wind Project |
4.250 |
|
24 |
1/5/133 |
Energia Customer Solutions Ltd. |
I.Q.Wind Ltd. |
Crocane Windfarm, Crocane, Cloyne, Midleton, Co. Cork |
Small Scale Wind Project |
1.700 |
|
25 |
1/5/134 |
Energia Customer Solutions Ltd. |
Pluckanes Windfarm Ltd. |
Pluckanes, Donoughmore, Co. Cork |
Small Scale Wind Project |
0.850 |
|
26 |
1/5/137 |
Energia Customer Solutions Ltd. |
Caher Downey Wind Farm Ltd. |
Caherdowney Windfarm, Caherdowney, Carriganimma, Macroom, Co. Cork |
Large Scale Wind Project |
10.000 |
|
27 |
1/5/139 |
Energia Customer Solutions Ltd. |
Venti Windfarm Energy Ltd. |
Curraghgraigue 2 Windfarm, Curraghgraigue Upper, Templederry, Nenagh, Co. Tipperary |
Small Scale Wind Project |
2.440 |
|
28 |
1/5/146 |
Energia Customer Solutions Ltd. |
Reirk Energy Ltd. |
Dromdeeveen Windfarm, Ballagh, Co. Limerick |
Large Scale Wind Project |
16.500 |
|
29 |
1/5/147 |
Energia Customer Solutions Ltd. |
Clydaghroe Windfarm Ltd. |
Clydaghroe Windfarm, Cummeennabuddoge, Clonkeen, Co. Kerry |
Small Scale Wind Project |
5.000 |
|
30 |
1/5/154 |
Energia Customer Solutions Ltd. |
Tullynamoyle Windfarm Ltd. |
Tullynamoyle Windfarm, Tullynamoyle, Killarga, Co. Leitrim |
Large Scale Wind Project |
9.000 |
|
31 |
1/5/155 |
Energia Customer Solutions Ltd. |
Ballaman Windfarm Ltd. |
Ballaman & Moneydurtlow, Tombrack, Ferns, Co. Wexford |
Small Scale Wind Project |
3.600 |
|
32 |
1/5/163 |
Bord Gáis Energy Ltd. |
Sigatoka Ltd. |
Garranereagh Windfarm, Lissarda, Co. Cork |
Large Scale Wind Project |
8.750 |
|
33 |
1/5/167 |
Statkraft Markets GmbH |
Castledockrell Wind Group Ltd. |
Castledockrell Windfarm, Ballenahillan, Ballycarney, Enniscorthy, Co. Wexford |
Large Scale Wind Project |
41.400 |
|
34 |
1/5/177 |
SWS Green Energy Ltd. |
BW2 Wind Farm Ltd. |
Booltiagh Windfarm Extension, Booltiagh, Connolly, Co. Clare |
Large Scale Wind Project |
12.000 |
|
35 |
1/5/178 |
Energia Customer Solutions Ltd. |
B9 Power Ltd. |
North Kerry Landfill Gas Project, Muingnaminnane, Tralee, Co. Kerry |
Biomass LFG |
1.00 |
|
36 |
1/5/182 |
Energia Customer Solutions Ltd. |
Arthur Davidson |
Aghadullagh Mill, Lismentan, Ballintra, Co. Donegal |
Hydro Project |
0.140 |
|
37 |
1/5/183 |
Flogas Enterprise Solutions Ltd. |
Starrus LFG Ltd. |
Ballynagran Residual Landfill (Phase 1), Ballynagran, Co. Wicklow |
Biomass LFG |
0.750 |
|
38 |
1/5/184 |
Flogas Enterprise Solutions Ltd. |
Starrus LFG Ltd. |
Connaught Regional Residual Landfill, Kilconnell, Co. Galway |
Biomass LFG |
0.660 |
|
39 |
1/5/185 |
SWS Green Energy Ltd. |
Lisheen Wind Farm II Ltd. |
Lisheen Windfarm II, Lisheen Mine, Killoran, Moyne, Thurles, Co. Tipperary |
Large Scale Wind Project |
24.000 |
|
40 |
1/5/186 |
Energia Customer Solutions Ltd. |
Ballycadden Windfarm Ltd. |
Ballycadden, Bolinrush, Lackendarragh, Bunclody, Co. Wexford |
Large Scale Wind Project |
14.450 |
|
41 |
1/5/187 |
SSE Airtricity Ltd. |
March Winds Ltd. |
Athea, Co. Limerick |
Large Scale Wind Project |
38.200 |
|
42 |
1/5/189 |
Burren Energy Supply Ltd. |
Knocknagoum Windfarm Ltd. |
Knocknagoum Windfarm, Lyrecrompane, Listowel, Co. Kerry |
Large Scale Wind Project |
41.300 |
|
43 |
1/5/190 |
SWS Green Energy Ltd. |
Knockacummer Wind Farm Ltd. |
Knockacummer, Co. Cork |
Large Scale Wind Project |
100.000 |
*Note that this plant will have a variable biodegradable fuel content, affecting the proportion of its exported electricity eligible for REFIT. This will be estimated ex-ante and will be certified for the purposes of REFIT calculations on an ex-post basis]
Annotations
Amendments:
F99
Substituted (17.12.2025) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2025 (S.I. No. 689 of 2025), art. 10 and sch. 1.
Editorial Notes:
E54
Previous affecting provision: schedule substituted (19.12.2024) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) (No. 2) Order 2024 (S.I. No. 756 of 2024), art. 3 and sch. 1; substituted (17.12.2025) as per F-note above.
E55
Previous affecting provision: schedule substituted (25.07.2024) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) (No. 1) Order 2024 (S.I. No. 377 of 2024), art. 3 and sch. 1; substituted (19.12.2024) as per E-note above.
E56
Previous affecting provision: schedule substituted (20.02.2023) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2023 (S.I. No. 119 of 2023), art. 13 and sch. 2; substituted (25.07.2024) as per E-note above.
E57
Previous affecting provision: schedule substituted (16.10.2021) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2021 (S.I. No. 532 of 2021), art. 3(a); substituted (20.02.2023) as per E-note above. Note apparent typo in art. 3(a) substituting sch. 1, not sch. 3. Note also reference to previous amendment by Order of 2019, art. 3(b), which appears to refer to S.I. No. 497 of 2019, art. 3(a).
E58
Previous affecting provision: schedule substituted (29.09.2019) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2019 (S.I. No. 497 of 2019), art. 3(a) and sch. 1; substituted (16.10.2021) as per E-note above.
E59
Previous affecting provision: schedule substituted (27.09.2018) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2018 (S.I. No. 403 of 2018), art. 3(e) and sch. 1; substituted (29.09.2019) as per E-note above.
E60
Previous affecting provision: schedule substituted (8.12.2016) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2016 (S.I. No. 600 of 2016), art. 3(c) and sch.; substituted (27.09.2018) as per E-note above.
E61
Previous affecting provision: schedule substituted (11.12.2015) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2015 (S.I. No. 556 of 2015), art. 3(d); substituted (8.12.2016) as per E-note above.
E62
Previous affecting provision: schedule substituted (19.12.2014) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2014 (S.I. No. 603 of 2014), art. 2(e); substituted (11.12.2015) as per E-note above.
E63
Previous affecting provision: schedule substituted (25.10.2013) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2013 (S.I. No. 421 of 2013), art. 3(g); substituted (19.12.2014) as per E-note above.
E64
Previous affecting provision: schedule substituted (31.10.2012) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2012 (S.I. No. 438 of 2012), art. 2(k); substituted (25.10.2013) as per E-note above.
E65
Previous affecting provision: schedule substituted (28.09.2011) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2011 (S.I. No. 513 of 2011), art. 2(d); substituted (31.10.2012) as per E-note above.
E66
Previous affecting provision: schedule substituted (3.11.2010) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2010 (S.I. No. 532 of 2010), art. 3b and sch.; substituted (28.09.2011) as per E-note above.
E67
Previous affecting provision: schedule substituted (3.11.2009) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2009 (S.I. No. 444 of 2009), art. 3(c); substituted (3.11.2010) as per E-note above.
E68
Previous affecting provision: schedule inserted (18.07.2008) by Electricity Regulation Act 1999 (Public Service Obligations) (Amendment) Order 2008 (S.I. No. 284 of 2008), art. 14 and sch.; substituted (3.11.2009) as per E-note above.