Planning and Development Act 2000
F1270[ Acknowledgement of completeness of certain applications under section 291
295A.—Where an application for permission for renewable energy development or repowering development is made to An Coimisiún Pleanála under section 291, An Coimisiún Pleanála shall, within 45 days of the receipt of the application —
(a) where it is satisfied that the application includes all the information required to process the application, acknowledge the completeness of the application by notice in writing to the applicant, or
(b) where it is not so satisfied, by notice in writing to the applicant request the applicant to submit a complete application without undue delay.]
Annotations
Amendments:
F1270
Inserted (6.08.2025) by European Union (Planning and Development) (Renewable Energy) Regulations 2025 (S.I. No. 274 of 2025), reg. 21, subject to transitional provisions in reg. 38.