97.—(1) In this section—

“applicant” includes a person on whose behalf a person applies for a certificate;

“the court” other than in subsections (19) and (21), means the Circuit Court for the circuit in which all or part of the development, to which the application under subsection (3) relates, is situated.

(2) For the purposes of this section—

(a) 2 or more persons shall be deemed to be acting in concert if, pursuant to an agreement, arrangement or understanding, one of them makes an application under subsection (3) or causes such an application to be made, and

(b) land in the immediate vicinity of other land shall be deemed in any particular case not to include land that is more than 400 metres from the land second-mentioned in this subsection.

(3) A person may, before applying for permission in respect of a development—

(a) consisting of the provision of F532[4 or fewer] houses, or

(b) for housing on land of F533[0.1 hectares] or less,

apply to the planning authority concerned for a certificate stating that section 96 shall not apply to a grant of permission in respect of the development concerned (in this section referred to as a “certificate”), and accordingly, where the planning authority grants a certificate, section 96 shall not apply to a grant of permission in respect of the development concerned.

(4) Subject to—

(a) subsections (6) and (12), and

(b) compliance by the applicant for a certificate with subsection (8),

a planning authority to which an application has been made under and in accordance with this section may grant a certificate to the applicant.

(5) An application for a certificate shall be accompanied by a statutory declaration made by the applicant—

(a) giving, in respect of the period of 5 years preceding the application, such particulars of the legal and beneficial ownership of the land, on which it is proposed to carry out the development to which the application relates, as are within the applicant’s knowledge or procurement,

(b) identifying any persons with whom the applicant is acting in concert,

(c) giving particulars of—

(i) any interest that the applicant has, or had at any time during the said period, in any land in the immediate vicinity of the land on which it is proposed to carry out such development, and

(ii) any interest that any person with whom the applicant is acting in concert has, or had at any time during the said period, in any land in the said immediate vicinity, of which the applicant has knowledge,

(d) stating that the applicant is not aware of any facts or circumstances that would constitute grounds under subsection (12) for the refusal by the planning authority to grant a certificate,

(e) giving such other information as may be prescribed.

(6) (a) A planning authority may require an applicant for a certificate to provide it with such further information or documentation as is reasonably necessary to enable it to perform its functions under this section.

(b) Where an applicant refuses to comply with a requirement under paragraph (a), or fails, within a period of 8 weeks from the date of the making of the requirement, to so comply, the planning authority concerned shall refuse to grant the applicant a certificate.

(7) A planning authority may, for the purpose of performing its functions under this section, make such further inquiries as it considers appropriate.

(8) It shall be the duty of the applicant for a certificate, at all times, to provide the planning authority concerned with such information as it may reasonably require to enable it to perform its functions under this section.

(9) The Minister may make regulations in relation to the making of an application under this section.

(10) Where a planning authority fails within the period of 4 weeks from—

(a) the making of an application to it under this section, or

(b) (in the case of a requirement under subsection (6)) the date of receipt by it of any information or documentation to which the requirement relates,

to grant, or refuse to grant a certificate, the planning authority shall on the expiry of that period be deemed to have granted a certificate to the applicant concerned.

(11) Particulars of a certificate granted under this section shall be entered on the register.

(12) A planning authority shall not grant a certificate in relation to a development if the applicant for such certificate, or any person with whom the applicant is acting in concert—

(a) has been granted, not earlier than 5 years before the date of the application, a certificate in respect of a development F534[on the land on which it is proposed to carry out the first-mentioned development or land in its immediate vicinity], and the certificate at the time of the application remains in force, or

(b) has carried out, or has been granted permission to carry out, a development referred to in subsection (3), not earlier than—

(i) 5 years before the date of the application, and

(ii) one year after the coming into operation of this section,

in respect of the land on which it is proposed to carry out the first-mentioned development, or land in its immediate vicinity, unless—

(I) the aggregate of any development to which paragraph (a) or (b) relates and the first-mentioned development would not, if carried out, exceed 4 houses, or

(II) (in circumstances where the said aggregate would exceed 4 houses) the aggregate of the land on which any development to which paragraph (a) or (b) relates, and the land on which it is proposed to carry out the first-mentioned development, does not exceed F535[0.1 hectares].

(13) Where a planning authority refuses to grant a certificate, it shall by notice in writing inform the applicant of the reasons for its so refusing.

(14) (a) Where a planning authority to which an application has been made under subsection (3) refuses to grant a certificate to the applicant, he or she may, not later than 3 weeks from the date on which the applicant receives notification of the refusal by the planning authority to grant the certificate, or such later date as may be permitted by the court, appeal to the court for an order directing the planning authority to grant to the applicant a certificate in respect of the development.

(b) The court may at the hearing of an appeal under paragraph (a)

(i) dismiss the appeal and affirm the refusal of the planning authority to grant the certificate, or

(ii) allow the appeal and direct the planning authority to grant the applicant a certificate in respect of the development concerned.

(15) A planning authority shall comply with a direction of the court under this section.

(16) (a) Subject to paragraph (b), a planning authority shall revoke a certificate, upon application in that behalf being made to it by the owner of land to which the certificate related, or by any other person acting with the permission of such owner.

(b) A planning authority shall not revoke a certificate under this subsection where permission has been granted in respect of the development to which the certificate relates.

(17) A person who, knowingly or recklessly—

(a) makes a statutory declaration under subsection (5), or

(b) in purported compliance with a requirement under subsection (6), provides a planning authority with information or documentation,

that is false or misleading in a material respect, or who believes any such statutory declaration made, or information or documentation provided in purported compliance with such requirement, by him or her not to be true, shall be guilty of an offence and shall be liable—

(i) on summary conviction to a fine not exceeding £1,500 or to imprisonment for a term not exceeding 6 months, or to both, or

(ii) on conviction on indictment to a fine not exceeding £500,000 or to imprisonment for a term not exceeding 5 years, or to both.

(18) A person who—

(a) forges, or utters, knowing it to be forged, a certificate purporting to have been granted under this section (hereafter in this subsection referred to as a “forged certificate”),

(b) alters with intent to deceive or defraud, or utters, knowing it to be so altered, a certificate (hereafter in this subsection referred to as an “altered certificate”), or

(c) without lawful authority or other reasonable excuse, has in his or her possession a forged certificate or an altered certificate,

shall be guilty of an offence and shall be liable—

(i) on summary conviction to a fine not exceeding £1,500 or imprisonment for a term not exceeding 6 months, or to both, or

(ii) on conviction on indictment to a fine not exceeding £500,000 or imprisonment for a term not exceeding 5 years, or to both.

(19) Where a person is convicted on indictment of an offence under subsection (17) or (18), the court may in addition to any fine or term of imprisonment imposed by the court under that subsection order the payment into court by the person of an amount that in the opinion of the court is equal to the amount of any gain accruing to that person by reason of the grant of a certificate on foot of the statutory declaration, information or documentation, as the case may be, to which the offence relates, and such sum shall, when paid in accordance with such order, stand forfeited.

(20) All sums that stand forfeited under subsection (19) shall be paid to the planning authority that granted the certificate concerned and shall be accounted for in the account referred to in section 96(13) and be applied only for the purposes specified in that section.

(21) Where a person is convicted of an offence under subsection (17), the court may revoke a certificate granted on foot of a statutory declaration, information or documentation to which the offence relates, upon application being made to it in that behalf by the planning authority that granted the certificate.

(22) A person shall not, solely by reason of having been granted a certificate, be entitled to a grant of permission in respect of the development to which the certificate relates.

Annotations

Amendments:

F531

Substituted (1.09.2015) by Urban Regeneration and Housing Act 2015 (33/2015), s. 36, S.I. No. 364 of 2015.

F532

Substituted (3.09.2021) by Affordable Housing Act 2021 (25/2021), s. 47(a), S.I. No. 450 of 2021.

F533

Substituted (24.12.2002) by Planning and Development (Amendment) Act 2002 (32/2002), s. 5, commenced on enactment.

F534

Inserted (3.09.2021) by Affordable Housing Act 2021 (25/2021), s. 47(b), S.I. No. 450 of 2021.

F535

Inserted (2.06.2003) by Local Government (No. 2) Act 2003 (17/2003), s. 5, commenced on enactment.

Editorial Notes:

E259

Power pursuant to section exercised (4.11.2021) by Planning and Development (Amendment) (No. 3) Regulations 2021 (S.I. No. 588 of 2021).

E260

Power pursuant to section exercised (10.09.2015) by Planning and Development (Amendment) (No. 3) Regulations 2015 (S.I. No. 387 of 2015).

E261

Power pursuant to section exercised (21.12.2006, 31.01.2007 and 31.03.3007) by Planning and Development Regulations 2006 (S.I. No. 685 of 2006).

E262

Power pursuant to section exercised (6.03.2003) by Planning and Development Regulations 2003 (S.I. No. 90 of 2003).

E263

Power pursuant to section exercised (11.03.2002) by Planning and Development Regulations 2002 (S.I. No. 70 of 2002).

E264

Power pursuant to section exercised (21.01.2002 and 11.03.2002) by Planning and Development Regulations 2001 (S.I. No. 600 of 2001).

E265

Previous affecting provision: subs. (3)(a) amended (1.09.2015) by Urban Regeneration and Housing Act 2015 (33/2015), s. 36, S.I. No. 364 of 2015; substituted as per F-note above.