Planning and Development Act 2000

F317[Supplementary provisions relating to ground source heat pumps and relevant solar energy development

34G

34G.(1) A planning authority shall make its decision on an application for permission for relevant solar energy development within the period of 8 weeks from the date of the notice referred to in section 34D(a).

(2) Paragraphs (b), (c), and (ca) of section 34(8) shall not apply to an application for permission for relevant solar energy development or development that is the installation of a ground source heat pump.

(3) Section 34(9) shall not apply to an application for permission for relevant solar energy development or development that is the installation of a ground source heat pump.]

Annotations

Amendments:

F317

Inserted (6.08.2025) by European Union (Planning and Development) (Renewable Energy) Regulations 2025 (S.I. No. 274 of 2025), reg. 5, subject to transitional provisions in reg. 38.