Planning and Development Act 2000

F356[Supplementary provisions relating to proposed development at Dublin Airport

34B

34B.(1)(a)(i) Where the planning authority receives an application under section 34 for development at the airport, it shall, as soon as is practicable after such receipt

(I) give a copy of the application to the competent authority, and

(II) enter into consultations with the competent authority for the purposes of giving such assistance as the competent authority may require in order to enable the competent authority, within 4 weeks of the competent authority receiving such copy, to either form the opinion referred to in subparagraph (iii) or to conclude that it is not of that opinion.

(ii) The competent authority shall, where it concludes that it is not of the opinion referred to in subparagraph (iii), as soon as is practicable after it so concludes, give notice in writing of that conclusion to the planning authority.

(iii) The following provisions of this section apply where the competent authority, in considering the application, forms the opinion that the development

(I) contains a proposal requiring the assessment for the need for a noise-related action, or

(II) indicates that a new operating restriction may be required.

(b) Subsections (1) to (3) of section 9 of the Aircraft Noise (Dublin Airport) Regulation Act 2019 shall, with all necessary modifications, apply to the performance by the competent authority of its functions under this section.

(c) Subsections (4) to (7) of section 9 of the Aircraft Noise (Dublin Airport) Regulation Act 2019 shall, with all necessary modifications, apply to measures and restrictions referred to in this section as those subsections apply to measures and restrictions referred to in those subsections.

(2) The competent authority shall, as soon as is practicable after it forms the opinion referred to in subsection (1)(a)(iii), give notice in writing to the planning authority of that opinion and the planning authority shall, as soon as is practicable after receiving the notice, consult with the competent authority in relation to, as appropriate, one or more of the following matters:

(a) any aspect of the development relating to noise that may arise in the operation of the development if it is carried out (including any such aspect relating to appropriate assessment or environmental impact assessment);

(b) any noise problem that would arise from the carrying out of the development as proposed, taking account of any noise mitigation measures or operating restrictions (if any), or any combination thereof, proposed in the application and any further information subsequently sought by the relevant authority from the applicant in relation to those matters and given by the applicant to the planning authority and the competent authority;

(c) where a noise problem would arise from the carrying out of the development as proposed

(i) any information on the application of the Balanced Approach to the consideration of the inclusion of noise mitigation measures or operating restrictions (if any), or any combination thereof, in the application and any further information subsequently sought by the relevant authority from the applicant in relation to those matters and given by the applicant to the planning authority and the competent authority,

(ii) whether noise mitigation measures or operating restrictions (if any), or any combination thereof, not proposed in the application are or is required and any information or plans subsequently sought by the relevant authority from the applicant in relation to such measures or restrictions, or combination thereof, as the case may be, and given by the applicant to the planning authority and the competent authority,

(iii) any information subsequently sought by the relevant authority from the applicant in relation to the application of the Balanced Approach to the noise mitigation measures or operating restrictions, or combination thereof, referred to in subparagraph (ii) and given by the applicant to the planning authority and the competent authority, and

(iv) subject to subsection (4), whether permission could, in so far as noise-related issues are concerned, be granted for the development subject to conditions specified by the competent authority relating to noise mitigation measures or operating restrictions (if any), or any combination thereof.

(3) (a) In subsection (2) and paragraph (b), relevant authority means the planning authority or the competent authority.

(b) Where the applicant gives any information or plans referred to in subsection (2) to one relevant authority, the applicant shall, on the same date (or as soon as is practicable thereafter), give copies of such information or plans, as the case may be, to the other relevant authority.

(4) Notwithstanding any other provision of this Act, the planning authority shall neither decide to refuse permission for the development nor decide to grant such permission subject to or without conditions until it receives a notice under subsection (5) or (14)(a)(ii) from the competent authority in respect of the application.

(5) (a) Paragraph (b) applies where the competent authority is satisfied that permission should not be granted for the development for the reason that inadequate provision has been made in the application (or in any plans or further information, or both, subsequently given by the applicant to the planning authority and the competent authority) to deal with the noise problem that would arise from the carrying out of the development as proposed.

(b) The competent authority shall, as soon as is practicable after it is so satisfied, give a notice in writing to the planning authority, stating the competent authoritys reasons why it is so satisfied, and directing the planning authority to refuse permission for the development.

(c) The planning authority shall comply with a direction given to it under paragraph (b) as soon as is practicable after it receives the notice concerned referred to in that paragraph and shall incorporate such notice in its decision to refuse permission for the development.

(d) Notwithstanding that a refusal referred to in paragraph (c) arises from a direction given by the competent authority to the planning authority, such refusal and the reasons for it shall, for the purposes of section 37 as read with section 37S, be treated as the decision, or part of the decision, as appropriate, of the planning authority on the application, and the other provisions of this Act shall be construed accordingly.

(6) Subsection (7) applies where the competent authority has applied the Balanced Approach to the noise problem referred to in subsection (2) and, in accordance with the Balanced Approach, assessed the noise mitigation measures or operating restrictions (if any), or any combination thereof, that may be required to be introduced as part of the development, and whether or not such measures or restrictions, or combination thereof, as the case may be, are or is in addition to, or in replacement of, one or more

(a) noise mitigation measures or operating restrictions (if any), or any combination thereof, proposed in the application, or

(b) existing noise mitigation measures or operating restrictions (if any), or any combination thereof.

(7) The competent authority shall, as soon as it is practicable for it to do so, by notice in writing given to the applicant and copied to the planning authority

(a) inform the applicant of the noise mitigation measures or operating restrictions (if any), or combination thereof, proposed to be required in a decision (if any) to grant permission for the development and its reasons for so proposing, and

(b) stating that the applicant may, within the period specified in the notice (being a period of not less than 4 weeks), make submissions or observations on such noise mitigation measures or operating restrictions (if any), or combination thereof, as the case may be, and on such reasons, including counterproposals, by notice in writing given to the competent authority and copied to the planning authority.

(8) The competent authority shall apply the Balanced Approach to its consideration of the counterproposals (if any) given to it by the applicant before the expiration of the period specified in the notice under subsection (7) concerned.

(9) Subject to subsection (10), the competent authority shall, as soon as is practicable after it complies with subsection (7) and, if applicable, subsection (8) and (at its discretion) having consulted with the applicant or any other person that it wishes to, in accordance with the Aircraft Noise Regulation and the Aircraft Noise (Dublin Airport) Regulation Act 2019, make, and publish on its website, a draft regulatory decision

(i) on the noise mitigation measures or operating restrictions (if any), or combination thereof, that it proposes to direct the planning authority to include as conditions of the planning authoritys decision (if any) to grant permission for the development, or

(ii) that no such conditions are required to be included in the planning authoritys decision (if any) to grant permission for the development.

(10) The competent authority shall prepare, and publish on its website on the same date as the draft regulatory decision, a report in relation thereto which shall state the competent authoritys reasons for such decision and include therein, as appropriate:

(a) a summary of the data examined (including any data relating to appropriate assessment or environmental impact assessment);

(b) the noise abatement objective;

(c) the measures considered to address any noise problem;

(d) an evaluation of the cost-effectiveness of the various measures considered;

(e) the application of the Balanced Approach;

(f) the identification of additional or alternative measures (other than those proposed in the draft regulatory decision) that have been considered;

(g) particulars of any proposed noise mitigation measures and operating restrictions (if any) to be introduced;

(h) if applicable, the reasons for the proposed introduction of any noise mitigation measures and operating restrictions (if any);

(i) the relevant technical information in relation to any proposed noise mitigation measures and operating restrictions (if any) to be introduced;

(j) a non-technical summary of such of the matters concerned referred to in paragraphs (a) to (i).

(11) The competent authority shall, as soon as is practicable after it complies with subsections (9) and (10), publish, in a national newspaper, a notice

(a) stating that the competent authority has

(i) made a draft regulatory decision under subsection (9), and

(ii) prepared the related report under subsection (10),

(b) stating particulars of how persons may view or otherwise have access to the draft regulatory decision and related report (which shall include being able to view the decision or report, or purchase a copy of the decision or report at a reasonable cost, at the offices of the competent authority during office hours),

(c) inviting persons to make submissions or observations in writing (and to provide a return address with such submissions or observations) in the specified form (if any) on the draft regulatory decision or related report, or both, before the expiration of 14 weeks beginning on the date of publication of the notice in the national newspaper, and

(d) stating particulars of the addresses (which shall include an electronic address) to which such submissions or observations may be sent.

(12) (a) The competent authority shall, as soon as is practicable after it complies with subsections (9) and (10), give each of the applicant, the airport authority and the planning authority copies of the draft regulatory decision that it made under subsection (9) and the related report that it prepared under subsection (10).

(b) For the avoidance of doubt, it is hereby declared that the applicant, the airport authority and the planning authority may each make submissions or observations referred to in subsection (11)(c) in accordance with that subsection.

(13) The competent authority shall, as soon as is practicable after the expiration of the 14 weeks referred to in subsection (11)(c) and having regard to the submissions and observations (if any) referred to in that subsection received by it within such 14 weeks

(a) make a regulatory decision consisting of the adoption by it of the draft regulatory decision made by it under subsection (9) without any amendments or with such amendments as it considers appropriate, and

(b) revise the related report prepared under subsection (11) to take into account such submissions and observations (if any) and such adoption and to state the competent authoritys reasons for such regulatory decision.

(14) The competent authority shall

(a) as soon as is practicable after it complies with subsection (13)

(i) publish on its website the regulatory decision it has adopted under subsection (13)(a) and the related report it has revised under subsection (13)(b), and

(ii) send a copy of such decision, together with a copy of the notice referred to in paragraph (b) (whether before or after the notice is published), to the applicant, the airport authority, the planning authority, the elected members of FCC, the elected members of Dáil Éireann in whose constituencies the airport is located and the return addresses of the persons who have made submissions or observations referred to in subsection (11)(c) in accordance with that subsection on the draft regulatory decision or related report concerned,

and

(b) as soon as is practicable after it complies with paragraph (a)(i), publish, in a national newspaper, a notice stating

(i) that the competent authority has adopted a regulatory decision under subsection (13)(a),

(ii) that the competent authority has revised the related report under subsection (13)(b),

(iii) particulars of how persons may view or otherwise have access to such regulatory decision and such related report (which shall include being able to view the decision or report, or purchase a copy of the decision or report at a reasonable cost, at the offices of the competent authority during office hours), and

(iv) that a right of appeal to the Board against the regulatory decision exists under section 37 as read with section 37R.

(15) (a) The planning authority shall incorporate the competent authoritys regulatory decision under subsection (13)(a), the subject of the notice given to the planning authority under subsection (14)(a)(ii), and the competent authoritys reasons for such decision in the planning authoritys decision on the application and shall do so regardless of whether the planning authoritys decision is to refuse permission for the development or to grant permission for the development.

(b) Notwithstanding that a regulatory decision referred to in paragraph (a) is made by the competent authority, such decision and the reasons for it shall, for the purposes of section 37 as read with section 37R, be treated as the decision, or part of the decision, as appropriate, of the planning authority on the application, and the other provisions of this Act shall be construed accordingly.

(c) The planning authority shall make its decision on the application as soon as is practicable after it receives, pursuant to subsection (14)(a)(ii), a copy of the competent authoritys regulatory decision under subsection (13)(a).

(16) Subject to subsection (17), a noise mitigation measure to be introduced by virtue of a regulatory decision adopted under subsection (13)(a) shall

(a) if no appeal under section 37 as read with section 37R is made, within the appropriate period referred to in section 37(1), against the planning authoritys decision on the application, come into effect on the expiration of such appropriate period, and

(b) after so coming into effect, remain in effect until revoked, or revoked and replaced, by the competent authority or the appeal body.

(17) The competent authority may, by notice published on its website on the same date as the regulatory decision adopted under subsection (13)(a) is, pursuant to subsection (14)(a), also so published

(a) authorise, for reasons stated in the notice, a lead in time for the coming into effect of a noise mitigation measure to be introduced by virtue of that decision, and

(b) specify the date, or the occurrence of the event, on which such noise mitigation measure shall come into effect.

(18) Subject to section 26 (b) of the Aircraft Noise (Dublin Airport) Regulation Act 2019, the competent authority shall, in relation to an operating restriction to be introduced by virtue of a regulatory decision adopted under subsection (13)(a), take such steps as it considers appropriate to cause Article 8 of the Aircraft Noise Regulation to be complied with as soon as is practicable after it applies to such restriction.

(19) Subject to subsection (20), an operating restriction referred to in subsection (18) shall

(a) come into effect on the day immediately following the day on which the operation of Article 8 of the Aircraft Noise Regulation ceases to further prevent the coming into effect of the operating restriction, and

(b) after so coming into effect, remain in effect until revoked, or revoked and replaced, by the competent authority or the appeal body.

(20) The competent authority may, by notice published on its website at any time before the day first-mentioned in subsection (19)(a)

(a) authorise, for reasons stated in the notice, a lead in time for the coming into effect of the operating restriction referred to in subsection (18), and

(b) specify the date, or the occurrence of the event, on which such operating restriction shall come into effect.

(21) Subsection (6) of section 34 shall not apply where the competent authority forms the opinion that a noise problem that would arise from the carrying out of the development as proposed would contravene materially the development plan or local area plan.]

Annotations

Amendments:

F356

Inserted (1.09.2019) by Aircraft Noise (Dublin Airport) Regulation Act 2019 (12/2019), s. 11, S.I. No. 403 of 2019.